Construction of Stormwater Box Culverts & associated works
Minnesota Road, Hamlyn Terrace
Value: – $1.3 million
Client: – Wyong Shire Council
Description: –
- Installation & continual monitoring of sediment and erosion control measures,
- Management of major waterflow through existing creeks and diversion around worksite using diversion channels and pumps,
- Demolition and removal of existing concrete pavement materials,
- Bulk Earthworks (1500m3 approx.) and detailed excavation for culvert slab footprint,
- Installation of a leanmix subbase underneath culvert slab footprint,
- Placement of formwork, steel reinforcement and 40MPa B80 Concrete to culvert slab,
- Installation of 144 Box Culverts 3.6m wide x 2.4m long x 0.9m high,
- Installation of up and downstream rip rap erosion protection,
- Placement of formwork, steel reinforcement and concrete to headwalls and edge beams
- Placement of Sandstone logs,